New analysis shows serious economic flaws in High Speed 2 plans

New research released

New research released today by the Institute of Economic Affairs, High Speed 2: the next government project disaster?, shows that the High Speed 2 (HS2) project is economically flawed. It reveals why the scheme is not commercially viable and asserts that taxpayers will bear a high proportion of the financial risks.

The research finds that policymakers in favour of HS2 are making their case on the basis of bogus assumptions:

Flawed economics

  • Huge government subsidies on the existing rail network mean that prices and demand levels are severely distorted.
  • Estimates made by the government of demand growth are very optimistic. The long timescale involved also adds to the uncertainty.

ØThe DfT’s Command Paper said demand for HS2 would be 267% higher by 2033. However, in the more recent Economic Case, it was said that this demand level would be reached by 2043 i.e. 10 years later.

  • The effect of competition from other rail lines has been ignored when projecting future HS2 ticket prices and passenger numbers. Lower prices would make the project even less viable.

ØCompetition from the West Coast Main Line or from the Chiltern Line could lead to the lowering of HS2 ticket prices in order to attract and retain customers.

  • The cost of HS2 will require a contribution of £1,000 per Income Tax payer
  • The project has been ‘gold-plated’, leading to grossly wasteful allocation of resources. The first five miles of the route, from Euston to Old Oak Common, for example, will add almost 25% (c. £4 billion) to the cost of the first phase but deliver negligible time savings.

ØAdditionally, the decision to route the line through the Chilterns will require major tunnelling work; this 18-mile stretch accounting for 17% of the construction costs

  • Significant environmental and social costs are not included in the assessment of the economic case, with several areas likely to be affected by ‘planning blight’.
  • HS2 is likely to create demand for additional high-cost, taxpayer-funded transport capacity. Terminating the line at Euston may require a new Underground line or Crossrail 2 link to cope with extra passenger numbers.

Exaggerated time savings

  • The case for HS2 assumes that time on board a train is wasted for business travellers. However, many business people are able to undertake productive work during part of their journeys. HS2’s claims are therefore greatly exaggerated.

ØFurther, the decision to build a new station on the outskirts of Birmingham city centre, as opposed to HS2 travelling direct to Birmingham New Street (the major transport hub of the West Midlands) will wipe out much of the time savings claimed.

Fraudulent ‘green’ credentials

  • The ‘green’ credentials of the scheme are highly questionable. At 225mph, the trains will be the fastest in Europe and will consume disproportionate levels of power via the National Grid.

ØHS2 simply constitutes a strategy of increasing public subsidy to enable more, CO2-consuming journeys

False regeneration claims

  • Claims that HS2 will bridge the north-south divide and bring regeneration should be treated with scepticism as the evidence is largely speculative. Alleged benefits must be set against the wider economic losses from the additional taxati